CALLPROJECT NUMBER & BIDDERS COUNTYBID DBE
001STP-0119(104)EQ S301-119-0.61 BARBOUR10.00
J. F. Allen Company772,359.10 10.00
R. H. Armstrong, Inc. 778,709.0510.00
Mountaineer Contractors 786,899.4510.00
Ohio Valley Paving Corp. 838,600.8110.00
Harman Construction842,076.14 16.86
002STP-0018(081)EQ S309-18-0.01 DODDRIDGE6.00
J. F. Allen Company229,499.75 6.00
Mountaineer Contractors 236,384.136.00
Dodd General Contractors 246,001.606.00
Carl Kelly Paving260,039.44 6.00
003STP-0060(137)EQ S310-60-1.23 FAYETTE8.00
West Virginia Paving 591,195.868.00
004STP-0033(158)EQ S311-33-22.25 GILMER10.00
J. F. Allen Company555,894.39 10.00
Carl Kelly Paving628,816.12 10.00
005STP-0020(132)EQ S317-20-4.64 HARRISON8.00
J. F. Allen Company309,976.43 8.00
R. H. Armstrong, Inc. 312,406.108.00
Mountaineer Contractors 316,815.708.00
Dodd General Contractors 325,150.428.00
Ohio Valley Paving Corp. 336,842.028.00
006STP-0016(111)EQ S323-16-5.44 LOGAN10.00
Mountain Enterprises 679,867.5810.00
007STP-0119(105)EQ S331-119-2.75 MONONGALIA6.00
Harman Construction525,259.55 14.20
Mountaineer Contractors 526,333.026.00
Dodd General Contractors 549,267.236.00
Ohio Valley Paving Corp. 554.831.756.00
J. F. Allen Company629,176.33 6.00
008STP-0007(129)EQ S339-7-15.58 PRESTON8.00
Harman Construction527,525.37 8.00
Mountaineer Contractors 533,337.148.00
Ohio Valley Paving Corp. 574,974.448.00
009STP-0032(012)EQ S342-32-0.00 RANDOLPH10.00
DEFERRED TO MARCH 24, 1998
010STP-0033(160)EQ S344-33-17.73 ROANE10.00
Carl Kelly Paving551,816.24 10.00
West Virginia Paving 585,621.4010.00
011STP-0250(100)EQ S325-250-9.59 MARION2.00
Mountaineer Contractors 316,722.702.00
J. F. Allen Company320,411.49 2.00
Dodd General Contractors 327,754.742.00
Ohio Valley Paving Corp. 338,811.932.00
Harman Construction351,337.24 4.03
012U328-104-0.57MERCER
Excavation Technologies 182,513.52
West Virginia Paving 210,497.18
Corte Construction245,522.12
013U333-522-12.00MORGAN
Union Equipment Co.213,581.40
014STP-0601(004)EQ U320-601-1.38 KANAWHA12.00
West Virginia Paving 232,420.5912.00
Orders Construction Co. 238,397.3112.00
015STP-0033(156)EQ S336-33-45.23 PENDLETON8.00
Kermit Butcher413,820.16 8.72
J. F. Allen Company441,555.87 8.00
Bean=s Lime and Stone 446,267.518.00
R. H. ArmstrongIRREGULAR
016STP-0072(058)EQ S347-72-22.00 TUCKER10.00
DEFERRED TO MARCH 24, 1998
017S334-3-3.15NICHOLAS
Waco Oil & Gas Co., Inc. 169,841.30
West Virginia Paving, Inc. 197,654.60
J. F. Allen Company226,048.75
018S338-66-12.99POCAHONTAS
Banam, Inc.217,290.00
BBR Drilling Company 221,235.00
Turman Construction Co. 257,402.50
019S328-29-0.10MERCER
Grandview Construction 38,652.20
Hoke Brothers Contracting 41,618.50
Corte Construction58,402.20
020S355-5-3.36WYOMING
DEFERRED TO MARCH 24, 1998
021BH-0052(106) S306-52-0.04 CABELL6.00
Ahern & Associates 7,330,000.006.00
National Engineering & Contracting 8,172,351.606.00
Edward Kraemer & Sons 8,299,359.526.00
Orders Construction Company 8,391,063.466.00
022S305-1-2.66BROOKE
Lash Excavating & Paving 84,126,75
Tri-state Asphalt Company 85,962.78
023S306-9-0.01CABELL
Mountain Enterprises, Inc. 57,727.45
West Virginia Paving 70,103.32
024S306-19-1.74CABELL
Mountain Enterprises, Inc. 68,410.98
West Virginia Paving 90,219.10
025S306-60-13.90CABELL
Mountain Enterprises, Inc. 46,549.04
West Virginia Paving 63,423.10
026S306-60/89-0.36CABELL
Mountain Enterprises, Inc. 18,831.98
West Virginia Paving 23,708.40
027S309-3-5.77DODDRIDGE
Dodd General Contractors 84,765.05
Ohio Valley Paving Corp. 90,778.45
Mountaineer Contractors 92,396.80
J. F. Allen Company 96,731.80
Carl Kelly Paving102,611.40
West Virginia Paving 114,904.25
028S309-5-11.41DODDRIDGE
Bilco Construction Company, Inc. 253,802.00
SMH Construction Co., Inc. 254,613.99
MEC Construction279,890.69
M & H Concrete Structures 285,230.33
Teays River Construction 299,229.92
Turman Construction Co. 316,489.65
Banam, Inc.319,670.10
029S309-15-3.06DODDRIDGE
DEFERRED TO MARCH 24, 1998
030S309-25-0.00DODDRIDGE
J. F. Allen Company74,380.65
Dodd General Contractors 77,212.35
Ohio Valley Paving Corp. 77,663.80
Mountaineer Contractors 83,972.50
Carl Kelly Paving85,417.50
West Virginia Paving 95,297.00
031S313-7/1-1.64GREENBRIER
Waco Oil & Gas, Inc. 57,335.00
West Virginia paving 65,608.70
032S314-5-3.82HAMPSHIRE
R. H. Armstrong150,191.00
Union Equipment Co.174,286.20
Carl Belt, Inc.194,637.00
IA Construction Corp. 205,343.80
033S315-208-0.01HANCOCK
Tri-State Asphalt 71,314.75
Lash Excavating & Paving 71,590.73
034S316-13-0.00HARDY
Bean=s Lime and Stone, Inc. 79,406.35
035S317-4-0.00HARRISON
Dodd General Contractors Corp. 98,712.76
Mountaineer Contractors 101,413.20
Ohio Valley Paving Corp. 102,108.90
J. F. Allen Company102,480.10
036S320-33-0.12KANAWHA
DEFERRED TO MARCH 24, 1998
037S320-59/2-0.00KANAWHA
West Virginia Paving 52,510.30
038S320-85-0.21KANAWHA
West Virginia Paving 83,920.05
039S321-19-3.34LEWIS
R. H. Armstrong160,710.00
J. F. Allen Company173,230.50
Dodd General Contractors 185,339.08
Mountaineer Contractors 195,785.40
040S321-33-12.92LEWIS
R. H. Armstrong131,938.18
Dodd General Contractors 141,779.60
Ohio Valley Paving141,957.10
Mountaineer Contractors 146,558.10
J. F. Allen Company146,999.13
041S322-46-10.80LINCOLN
West Virginia Paving 58,481.30
042S323-11/1-0.00L0GAN
Mountain Enterprises 29,694.00
043S323-73-2.27LOGAN
Mountain Enterprises 78,350.07
044S324-52-22.15MCDOWELL
West Virginia Paving 46,135.22
Bluestone Paving60,939.50
045S325-218-11.53MARION
J. F. Allen Company72,944.60
Dodd General Contractors Corp. 75,857.85
Ohio Valley Paving Corp. 78,503.40
Mountaineer Contractors 84,116.00
Harman Construction87,944.00
046S327-35-16.11MASON
West Virginia Paving 108,316.57
Carl Kelly Paving126,586.44
047S327-41-4.99MASON
West Virginia Paving 209,626.23
048S328-10/11-0.00MERCER
West Virginia Paving 35,025.00
Bluestone Paving 42,945.00
049S328-19-12.86MERCER
West Virginia Paving 65,308.32
Bluestone Paving75,172.50
050S329-42-3.38MINERAL
R. H. Armstrong127,150.75
Carl Belt, Inc.160,235.75
IA Construction Corp. 166,217.60
051S330-49-3.68MINGO
Mountain Enterprises 116,813.60
052S330-80-4.60MINGO
Mountain Enterprises 106,834.50
053S334-7-0.10NICHOLAS
Waco Oil & Gas C., Inc. 59,738.50
West Virginia Paving 60,012.00
054S336-220-9.60PENDLETON
Kermit Butcher84,040.90
R. H. Armstrong86,867.00
J. F. Allen Company89,665.54
Bean=s Lime and Stone 98,189.50
055S339-70-0.19PRESTON
Ohio Valley Paving Corp. 66,581.55
Dodd General Contractors Corp. 66,666.66
Mountaineer Contractors 67,996.75
Harman Construction69,291.54
J. F. Allen Company72,320.44
R. H. Armstrong77,393.25
056S340-6-5.97PUTNAM
Teays River Construction Co. 358,755.39
SMH Construction Co., Inc. 375,139.92
Bilco Construction Company, Inc. 380,648.00
Banam, Inc.387,934.20
McCoy Construction388,069.20
M & H Concrete Structures 398,706.78
Wiseman Construction Company 479,773.20
057S341-6-0.00RALEIGH
West Virginia Paving 63,991.71
Bluestone Paving80,467.50
058S341-16-17.29RALEIGH
West Virginia Paving 63,312.77
Bluestone Paving69,981.00
059S345-20-0.00SUMMERS
West Virginia Paving 80,922.83
Bluestone Paving92,525.00
060S347-7-2.75TUCKER
R. H. Armstrong74,689.50
Kermit Butcher81,252.50
J. F. Allen Company82,116.80
Harman Construction89,869.30
061S348-23-0.00TYLER
Klug Bros., Inc.224,576.20
J. F. Allen Company259,900.26
West Virginia Paving 260,131.20
Carl Kelly Paving260,329.80
062S350-3-0.01WAYNE
Mountain Enterprises 83,131.30
063S355-85-7.38WYOMING
West Virginia Paving 155,551.59
Mountain Enterprises 164,410.23