West Virginia Department Of Transportation
Division of Highways
Bid Results - Letting of February 5, 2002
CALL |
PROJECT NUMBER & BIDDERS |
COUNTY |
BID |
DBE |
001 |
STP-0003(086)E (U341-3-35.59) |
Raleigh |
4.00 |
|
Orders Construction Company, Inc. |
3,794,043.42 |
4.00 |
||
Ahern & Associates, Inc. |
4,030,000.00 |
4.00 |
||
002 |
S304-79-49.28-02 |
Braxton |
||
Meadows Stone & Paving, Inc. |
678,526.25 |
|||
Ground Breakers, Inc. |
699,999.00 |
|||
Sunrise Construction Company, Inc. |
701,674.00 |
|||
Green River Group. LLC |
703,212.50 |
|||
Teays River Construction Company |
761,016.67 |
|||
Orders Construction Company, Inc. |
784,770.40 |
|||
Carpenter Reclamation, Inc. |
879,605.00 |
|||
Dingess Transport, Inc. |
Irregular |
|||
003 |
STP-0051(020)E (U302-51-4.44) |
Berkeley |
8.00 |
|
DEFERRED TO FEBRUARY 20, 2002 |
||||
004 |
STP-0060(173)E (S306-60-12.61) |
Cabell |
||
Mountain Enterprises, Inc. |
122,602.20 |
|||
West Virginia Paving, Inc. |
153,303.48 |
|||
005 |
STP-0060(175)E (S306-60-4.43) |
Cabell |
10.00 |
|
Mountain Enterprises, Inc. |
257,379.93 |
10.00 |
||
West Virginia Paving, Inc. |
339,172.00 |
10.00 |
||
006 |
STP-0060(174)E (S306-60-24.69) |
Cabell |
5.00 |
|
West Virginia Paving, Inc. |
181,337.72 |
5.00 |
||
Mountain Enterprises, Inc. |
203,530.26 |
5.00 |
||
Skilton Contracting of WV, LLC |
209,963.38 |
10.00 |
||
Mountaineer Contractors, Inc. |
231,119.00 |
5.00 |
||
007 |
NH-0019(240)E (S310-19-5.75) |
Fayette |
5.00 |
|
West Virginia Paving, Inc. |
1,650,374.50 |
5.00 |
||
Mountaineer Contractors, Inc. |
1,657,287.00 |
5.00 |
||
008 |
IM-0773(179)E (S318-77-124.90) |
Jackson |
7.00 |
|
Orders Construction Company, Inc. |
1,552,852.30 |
7.00 |
||
Ahern & Associates, Inc. |
1,588,800.00 |
7.00 |
||
Becdir Construction Company, Inc. |
1,633,820.00 |
7.00 |
||
Bilco Construction Company, Inc. |
1,697,765.00 |
7.00 |
||
009 |
STP-0033(224)E (S318-33-17.81) |
Jackson |
8.00 |
|
West Virginia Paving, Inc. |
228,192.13 |
8.00 |
||
Carl Kelly Paving, Inc. |
236,387.89 |
8.00 |
||
010 |
BR-0033(176)E (S318-33-13.70) |
Jackson |
7.00 |
|
The Righter Company, Inc. |
1,979,734.50 |
7.00 |
||
Teay River Construction Company, Inc. |
2,084,406.53 |
7.00 |
||
Roberts Construction Company |
2,191,101.58 |
7.00 |
||
Orders Construction Company, Inc. |
2,459,445.02 |
7.00 |
||
Ahern & Associates, Inc. |
2,466,000.00 |
7.00 |
||
011 |
S328-71-3.80 |
Mercer |
||
Turman Construction Co. |
979,233.05 |
|||
Bilco Construction Company, Inc. |
1,050,874.00 |
|||
Orders Construction Company, Inc. |
1,064,224.09 |
|||
Roberts Construction Company |
1,130,637.40 |
|||
Corte Construction Co., Inc. |
1,169,695.20 |
|||
Teays River Construction Company, Inc. |
1,373,876.00 |
|||
012 |
BR-0100(011)E (S331-100-3.97) |
Monongalia |
5.00 |
|
Ohio-West Virginia Excavating Co., Inc. |
629,564.00 |
5.00 |
||
Bilco Construction Company, Inc. |
690,317.00 |
5.00 |
||
Teays River Construction Company, Inc. |
762,278.50 |
5.00 |
||
013 |
STP-0036(032)E (S334-36-23.47) |
Roane |
11.00 |
|
West Virginia Paving, Inc. |
545,905.09 |
11.00 |
||
Carl Kelly Paving, Inc. |
568,905.69 |
11.00 |
||
Meadows Stone & Paving, Inc. |
678987.60 |
11.00 |
||
014 |
S349-30-4.11 |
Upshur |
||
C. L. Belt Construction, Inc. |
611,271.41 |
|||
Bilco Construction Company, Inc. |
617,543.00 |
|||
SMH Construction Co., Inc. |
660,917.90 |
|||
Hoke Brothers Contracting |
687,640.20 |
|||
Turman Construction Co. |
708,320.32 |
|||
Meadows Stone & Paving, Inc. |
718,306.51 |
|||
C & R Builders, Inc. |
723,009.03 |
|||
Orders Construction Company, Inc. |
726,524.73 |
|||
Teays River Construction Company, Inc. |
728,456.65 |
|||
Polino Contracting, Inc. |
838,847.80 |
|||
Corte Construction Co., Inc. |
939,287.00 |
|||
015 |
NH-0050(194)E (S354-50-5.76) |
Wood |
10.00 |
|
West Virginia Paving, Inc. |
912,751.85 |
10.00 |
||
Carl Kelly Paving, Inc. |
964,064.58 |
10.00 |
||
016 |
BR-0016(131)E (S355-16-1.71) |
Wyoming |
6.00 |
|
C. L. Belt Construction, Inc. |
653,140.97 |
51.00 |
||
SMH Construction Company, Inc. |
664,103.78 |
6.00 |
||
Bilco Construction Company, Inc. |
673,158.00 |
6.00 |
||
Turman Construction Co. |
709,417.63 |
6.00 |
||
Roberts Construction Company, Inc. |
762,229.84 |
6.00 |
||
Hoke Brothers, Inc. |
795,823.00 |
6.00 |
||
Orders Construction Company, Inc. |
860,674.10 |
6.00 |
||
Teays River Construction Company, Inc. |
900,930.50 |
6.00 |
||
Vecellio & Grogan, Inc. |
1,061,026.65 |
6.00 |
||
017 |
S323-10/10-0.01 |
Logan |
||
C. L. Belt Construction, Inc. |
374,881.94 |
|||
Bilco Construction Company, Inc. |
387,478.00 |
|||
Hoke Brothers, Inc. |
398,304.64 |
|||
McCoy Construction Company |
424,889.40 |
|||
SMH Construction Company, Inc. |
428,319.99 |
|||
Teays River Construction Company, Inc. |
442,700.00 |
|||
Roberts Construction Company, Inc. |
447,094.20 |
|||
Orders Construction Company, Inc. |
451,850.34 |
|||
018 |
S352-7-33.52 |
Wetzel |
||
SMH Construction Company, Inc. |
525,798.44 |
|||
Bilco Construction Company, Inc. |
534,575.00 |
|||
Orders Construction Company, Inc. |
581,360.65 |
|||
Savage Construction Company, Inc. |
588,475.47 |
|||
Teays River Construction Company, Inc. |
596,272.27 |
|||
Lone Pine Construction, Inc. |
628,209.76 |
|||
Ohio-West Virginia Excavating Co., Inc. |
647,744.63 |
|||
Lang Brothers, Inc. |
659,532.24 |
|||
019 |
E315-2-1.11 |
Hancock |
||
Brayman Construction Corporation |
140,000.00 |
|||
Orders Construction Company, Inc. |
156,632.99 |
|||
Bilco Construction Company, Inc. |
158,522.00 |
|||
Mosites Construction Company |
207,633.00 |
|||
Ahern & Associates, Inc. |
225,000.00 |
|||