CALL | PROJECT NUMBER & BIDDERS | COUNTY | BID | DBE |
001 | STP-0016(110)EQ S307-16-16.67 | CALHOUN | 12.00 | |
Carl Kelly Paving Inc. | 637,552.53 | 12.00 | ||
West Virginia Paving Inc. | 782,564.48 | 12.00 | ||
002 | NH-0052(153)E S324-52-16.25 | MCDOWELL | 12.00 | |
West Virginia Paving Inc. | 574,192.14 | 12.00 | ||
003 | STP-0050(136)EQ S314-50-0.01 | HAMPSHIRE | 10.00 | |
R. H. Armstrong Inc. | 795,865.32 | 10.00 | ||
Carl Belt Inc. | 1,015, 949.94 | 10.00 | ||
004 | STP-0033(159)EQ S318-33-14.69 | JACKSON | 8.00 | |
Carl Kelly Paving Inc. | 339,659.20 | 8.00 | ||
West Virginia Paving Inc. | 350,048.54 | 8.00 | ||
005 | STP-0016(109)EQ S337-16-0.01 | PLEASANTS | 10.00 | |
Dodd General Contractors Corp. | 296,182.17 | 10.00 | ||
Carl Kelly Paving Inc. | 324,708.10 | 10.00 | ||
West Virginia Paving Inc. | 371,386.35 | 10.00 | ||
006 | STP-0071(015)EQ S328-71-0.00 | MERCER | 10.00 | |
Bluestone Paving Inc. | 347,201.47 | 13.50 | ||
West Virginia Paving Inc. | 352,832.17 | 10.00 | ||
007 | NH-0035(108)E S340-35-21.21 | PUTNAM | ||
West Virginia Paving Inc. | 232,272.65 | |||
008 | ER-0596(002)E E323-44-E04.41 | LOGAN | ||
Turman Construction Co. | 296,070.63 | |||
B.B.R. Drilling Company | 425,753.39 | |||
009 | STP-0003(078)EQ S341-3-10.08 | RALEIGH | 12.00 | |
West Virginia Paving Inc. | 842,875.17 | 12.00 | ||
010 | NH-0002(282)E S354-2-23.06 | WOOD | 10.00 | |
Carl Kelly Paving Inc. | 328,323.03 | 10.00 | ||
West Virginia Paving Inc. | 335,497.98 | 10.00 | ||
011 | NH-0119(018)E S303-119-4.40 | BOONE | 10.00 | |
West Virginia Paving Inc. | 1,516,410.08 | 10.00 | ||
012 | NH-0050(134)E S317-50-15.46 | HARRISON | 12.00 | |
DEFERRED TO MAY 6, 1998 | ||||
013 | STP-0250(101)EQ S342-250-6.00 | RANDOLPH | 8.00 | |
R.H. Armstrong Inc. | 433,331.11 | 8.00 | ||
Kermit Butcher | 461,782.12 | 33.23 | ||
J.F. Allen Company | 514,699.37 | 8.00 | ||
014 | STP-0014(038)EQ S354-A14-0.00
NFA-0014(043) S354-A14-0.00-02 | WOOD | 10.00 | |
Mountaineer Contractors Inc. | 2,217,080.31 | 10.00 | ||
Alan Stone Co., Inc. | 2,355,814.74 | 10.00 | ||
Ahern & Associates Inc. | 2,510,000.00 | 10.00 | ||
Carl Kelly Paving Inc. | 2,532,694.69 | 10.00 | ||
Turman Construction Co. | 2,577,800.25 | 10.00 | ||
Orders Construction Company | 2,879,536.44 | 10.00 | ||
015 | STP-0003(084)EQ S303-3-40.73 | BOONE | 10.00 | |
West Virginia Paving Inc. | 750,679.96 | 10.00 | ||
016 | S330-3/12-4.13 | MINGO | ||
McCoy Construction Company | 261,217.00 | |||
Teays River Construction Company | 268,286.00 | |||
Upon This Rock Construction | 291,000.00 | |||
M & H Concrete Structures Inc. | 319,830.00 | |||
Roberts Construction Co. | 348,418.50 | |||
Banam Inc. | 367,091.50 | |||
Bilco Construction Company Inc. | 376,011.00 | |||
017 | S341-305-2.77 & S341-305-2.79 | RALEIGH | ||
SMH Construction Co., Inc. | 465,331.41 | |||
Teays River Construction Company | 491,083.18 | |||
Bilco Construction Company Inc. | 552,969.00 | |||
Turman Construction Co. | 558,160.60 | |||
Upon This Rock Construction | 571,000.00 | |||
018 | IM-77-3(278)E S354-77-168.50 NH-64-2(99)E S320-64-50.11 | VARIOUS | ||
West Virginia Paving Inc. | 1,347,104.00 | |||
019 | E313-64-168.00 | GREENBRIER | ||
DEFERRED TO MAY 6, 1998 | ||||
020 | S329-2-4.76 | MINERAL | ||
IA Construction Corp. | 239,822.40 | |||
C.D. Alt Inc. | 316,094.00 | |||
Nelson Excavating Inc. | 370,934.70 | |||
021 | S381-HER/B-98.00 | VARIOUS | ||
Chemi-Trol Chemical Co. | 17,279.36 | |||
Deangelo Brothers Inc. | 21,524.72 | |||
022 | S383-HER/B-98.00 | VARIOUS | ||
Chemi-Trol Chemical Co. | 14,206.22 | |||
Deangelo Brothers Inc. | 21,593.45 | |||
023 | S384-HER/B-98.00 | VARIOUS | ||
PULLED | ||||
024 | S385-HER/B-98.00 | BERKELEY | ||
Deangelo Brothers Inc. | 4,176.12 | |||
025 | S386-HER/B-98.00 | OHIO | ||
Deangelo Brothers Inc. | 3,116.47 | |||
Chemi-Trol Chemical Co. | 5,433.12 | |||
026 | S387-HER/B-98.00 | VARIOUS | ||
DEFERRED TO MAY 6, 1998 | ||||
027 | S388-HER/B-98.00 | RANDOLPH | ||
Deangelo Brothers Inc. | 1,975.85 | |||
028 | S389-HER/B-98.00 | VARIOUS | ||
Chemi-Trol Chemical Co. | 19,455.22 | |||
Deangelo Brothers Inc. | 19.928.06 | |||
029 | S331-7/18-1.38 | MONONGALIA | ||
SMH Construction Co., Inc. | 205,693.07 | |||
Bilco Construction Company | 218,243.00 | |||
Teays River Construction Company | 241,904.61 | |||
MEC Construction Inc. | 253,057.56 | |||
Upon This Rock Construction | 271,000.00 | |||
030 | S331-705-1.69 | MONONGALIA | ||
Bayliss & Ramey Inc. | 27,507.00 | |||
West Virginia Signal & Light Inc. | 34,942.80 | |||
Hickman Electric Corp. | 62,439.00 | |||
031 | S334-19/25-0.09 | NICHOLAS | ||
Banam Inc. | 180,587.40 | |||
McCoy Construction Company | 185,987.94 | |||
Grandview Construction Inc. | 189,119.32 | |||
Hoke Brothers Contracting | 194,267.31 | |||
M & H Concrete Structures Inc. | 207,455.11 | |||
Teays River Construction Company | 207,884.00 | |||
Bilco Construction Company Inc. | 225,911.00 | |||
Orders Construction Company Inc. | 236,079.29 | |||
Upon This Rock Construction | 287,000.00 | |||
032 | U341-19-12.90 | RALEIGH | ||
Bayliss & Ramey Inc. | 24,103.50 | |||
West Virginia Signal & Light Inc. | 36,992.80 | |||
033 | S335-15-0.89 | OHIO | ||
DEFERRED TO MAY 6, 1998 | ||||
034 | G016-HCM/H-1.00 | HARDY | ||
Harco Construction Company | 474,247.00 | |||
C.D. Alt Inc. | 477,500.00 | |||
Trimble Engineers | 586,985.00 | |||