West Virginia Department Of Transportation
Division of Highways
Bid Results - Letting of September 18, 2001
CALL | PROJECT NUMBER & BIDDERS | COUNTY | BID |
DBE |
001 | APD-0484(135)CTC (X316-H-117.40-04) | Hardy | 4.00 |
|
DEFERRED TO September 25, 2001 | ||||
002 | DPC-0042(052)C (U319-9-10.70-08) | Jefferson | 5.00 |
|
DEFERRED TO September 25, 2001 | ||||
003 | X305-13/1-0.00-02 | Brooke | ||
Savage Construction Company, Inc. | 99,943.10 |
|||
Ohio-West Virginia Excavating Co., Inc. | 115,952.50 |
|||
Mountaineer Contractors, Inc. | 137,587.80 |
|||
004 | S308-16-35.08 | Clay | ||
DEFERRED TO OCTOBER 2, 2001 | ||||
005 | S310-85/5-2.94 | Fayette | ||
DEFERRED TO OCTOBER 2, 2001 | ||||
006 | IM-0773(333)E (S320-77-114.64) | Jackson | 5.00 |
|
West Virginia Paving, Inc. | 1,299,628.45 |
5.00 |
||
Carl Kelly Paving, Inc. | 1,479,272.74 |
5.00 |
||
Mountaineer Contractors, Inc. | 1,584,031.00 |
5.00 |
||
Skilton Contracting of WV, LLC | 1,588,674.40 |
5.00 |
||
007 | NH-0068(092)E (S331-68-4.20) | Monongalia | 3.00 |
|
Ahern & Associates, Inc. | 656,100.00 |
3.00 |
||
Orders Construction Company, Inc. | 730,889.60 |
3.00 |
||
Becdir Construction Company, Inc. | 763,220.90 |
3.00 |
||
The Velotta Company | Irregular |
|||
008 | U339-7/12-0.06-12 | Preston | ||
Ground Breakers, Inc. | 956,446.65 |
|||
Mountaineer Contractors, Inc. | 961,214.00 |
|||
Turman Construction Co. | 992,378.90 |
|||
Teays River Construction Company | 996,389.80 |
|||
Laurita Excavating, Inc. | 998,021.13 |
|||
A. L. L. Construction, Inc. | 1,017,238.46 |
|||
Green River Group, LLC | 1,021,979.46 |
|||
009 | OCRO-2001(021)E (S320-ATT/EN-2.00) | Kanawha | ||
DEFERRED OCTOBER 2, 2001 | ||||
010 | S306-101/1-0.00 | Cabell | ||
Mountain Enterprises, Inc. | 56,716.81 |
|||
West Virginia Paving, Inc. | 68,218.00 |
|||
Mountaineer Contractors, Inc. | 71,051.45 |
|||
011 | S306-160/29-0.00 | Cabell | ||
Mountain Enterprises, Inc. | 57,590.70 |
|||
West Virginia Paving, Inc. | 74,705.50 |
|||
Mountaineer Contractors, Inc. | 77,608.45 |
|||
012 | S306-35-3.83 | Cabell | ||
Mountain Enterprises, Inc. | 32,382.22 |
|||
Skilton Contracting of WV, LLC | 42,114.50 |
|||
West Virginia Paving, Inc. | 46,261.00 |
|||
Mountaineer Contractors, Inc. | 46,373.90 |
|||
013 | OCRO-2000(005)E (U399-GRD/L-99.00-2) | Kanawha | ||
Green Acres Contracting Company, Inc. | 196,267.75 |
|||
SMH Construction Co., Inc. | 430,169.63 |
|||
Penn Line Service, Inc. | 542,600.00 |
|||
014 | S350-60-3.22 | Wayne | ||
Mountain Enterprises, Inc. | 120,791.54 |
|||
015 | S350-52-27.47 | Wayne | ||
Mountain Enterprises, Inc. | 57,750.38 |
|||
016 | U314-220-7.44 | Hampshire | ||
A. L. L. Construction, Inc. | 242,892.88 |
|||
JA Goldizen, Inc. | 299,478.00 |
|||
Laurita Excavating, Inc. | 301,043.50 |
|||
Ground Breakers, Inc. | 314,259.10 |
|||
Belt Paving, Inc. | 393,724.80 |
|||
017 | S330-3/5-20.12 | Mingo | ||
McCoy Construction Company | 919,721.30 |
|||
Roberts Construction Company | 929,872.95 |
|||
Bilco Construction Company, Inc. | 1,048,134.00 |
|||
018 | S303-17-8.83 | Boone | ||
West Virginia Paving, Inc. | 209,106.61 |