West Virginia Department Of Transportation
Division of Highways
Bid Results - Letting of July 13, 2004
CALL |
PROJECT NUMBER & BIDDERS |
COUNTY |
BID |
DBE |
001 |
STP-0027(035)E (S305-27-0.02) |
Brooke |
10.00 |
|
Carl Kelly Paving, Inc. |
448,217.93 |
10.00 |
||
Lash Excavating & Paving |
450,173.50 |
10.00 |
||
002 |
S311-12/7-0.00 |
Gilmer |
||
Bilco Construction Company, Inc. / O. K. Construction Company, Inc. |
542,611.00 |
|||
MEC Construction, Inc. |
589,841.30 |
|||
Hoke Brothers Contracting |
602,322.33 |
|||
Teays River Construction Company |
624,364.30 |
|||
Meadows Stone & Paving, Inc. |
648,169.33 |
|||
Turman Construction Co. |
688,487.75 |
|||
Orders Construction Company, Inc. |
689,494.15 |
|||
SMH Construction Co., Inc. |
691,448.85 |
|||
003 |
STP-0230(001)E (U319-230-4.34) |
Jefferson |
8.00 |
|
A.L.L. Construction, Inc. |
687,141.87 |
8.00 |
||
Mountaineer Contractors, Inc. |
788,783.41 |
8.00 |
||
Jim Construction, Inc. |
792,469.60 |
8.00 |
||
004 |
STPG-0060(184)E (S320-60-11.55) |
Kanawha |
3.00 |
|
Davis H. Elliot Company, Inc. |
360,622.00 |
3.00 |
||
Bayliss & Ramey, Inc. |
394,199.68 |
3.00 |
||
West Virginia Signal and Light, Inc. |
429,008.70 |
3.00 |
||
Stealth, LTD |
451,422.70 |
3.00 |
||
005 |
STP-0007(161)E (U331-7-34-84) |
Monongalia |
7.00 |
|
Mountaineer Contractors, Inc. |
1,622,380.00 |
7.00 |
||
006 |
STPG-0219(260)E (U342-219-41.90) |
Randolph |
||
Glem Company |
95,531.40 |
|||
Davis H. Elliot Company, Inc. |
96,689.00 |
|||
Stealth, LTD |
97,500.00 |
|||
Bayliss & Ramey, Inc. |
101,652.19 |
|||
West Virginia Signal and Light, Inc. |
129,306.90 |
|||
007 |
BR-0119(047)E (S346-119-7.94) |
Taylor |
3.00 |
|
MEC Construction, Inc. |
3,377,634.20 |
3.00 |
||
Orders Construction Company, Inc. |
3,458,347.99 |
3.00 |
||
Bilco Construction Company, Inc. / O. K. Construction Company, Inc. |
3,657,243.00 |
3.00 |
||
Mosites Construction Company |
4,125,525.38 |
3.00 |
||
Ahern & Associates, Inc. |
4,153,200.00 |
3.00 |
||
008 |
S349-32-8.59 |
Upshur |
||
Bilco Construction Company, Inc. / O. K. Construction Company, Inc. |
196,199.00 |
|||
SMH Construction Co., Inc. |
207,408.78 |
|||
C L Belt Construction, Inc. |
212,000.00 |
|||
Meadows Stone & Paving, Inc. |
215,443.50 |
|||
Teays River Construction Company |
229,848.75 |
|||
Hoke Brothers Contracting |
238,333.87 |
|||
MEC Construction, Inc. |
249,923.18 |
|||
Orders Construction Company, Inc. |
265,633.80 |
|||
Turman Construction Co. |
271,879.50 |
|||
009 |
NH-0050(199)E (S354-50-0.02) |
Wood / Doddridge |
||
DEFERRED TO JULY 27, 2004 |
||||
010 |
S302-9/30-0.23 |
Berkeley |
||
The Velotta Company |
152,303.30 |
|||
Orders Construction Company, Inc. |
153,405.90 |
|||
Ahern & Associates, Inc. |
1`57,800.00 |
|||
011 |
S329-28/1-0.00 |
Mineral |
||
Belt Paving, Inc. |
91,345.70 |
|||
IA Construction Company |
94,443.45 |
|||
012 |
U341-19-17.65 |
Raleigh |
||
Davis H. Elliot Company, Inc. |
79,122.00 |
|||
Glem Company |
88,533.50 |
|||
Bayliss & Ramey, Inc. |
96,492.23 |
|||
West Virginia Signal and Light, Inc. |
99,136.60 |
|||
Stealth, LTD |
115,865.10 |