District One:
Roads to Prosperity (RTP) projects
Since 2017 to October 2019:
Have completed 108.09 miles of RTP resurfacing projects at a cost of $11,953,342
Replaced 2 bridges at a cost of $3,603,088
Repaired 20 slides at a cost of $5,766,668
From October to end of year, 2019
Will spend another $24,444,775 on 29.70 miles by end of 2019 on RTP resurfacing projects
Will replace 2 bridges at a cost of $23,806,155
Will repair 8 slides at a cost of $2,127,915
Secondary Roads Maintenance Initiative (as of October 17, 2019)
Paved 71.41 miles
Ditched 478.88 miles
Mowed 3,004.30 miles
Patched 1,085.52 miles
District Two
Roads to Prosperity (RTP) projects
Since 2017 to October 2019
Have completed 123.55 miles of RTP resurfacing projects at a cost of $72,125,882 (includes I-64 GARVEE project)
Replaced 4 bridges at a cost of $5,579,065
Repaired 12 slides at a cost of $2,905,830
Replaced 3 culverts at a cost of $989,493
From October to end of year, 2019
Will spend another $1,021,652 on 7.41 miles by end of 2019 on RTP resurfacing projects
Will replace 3 bridges at a cost of $2,131,688
Will repair 9 slides at a cost of $3,065,726
Secondary Roads Maintenance Initiative (as of October 17, 2019)
Paved 123.96 miles
Ditched 795.57 miles
Mowed 3,787.87 miles
Patched 2,251.14 miles
District Three
Roads to Prosperity (RTP) projects
Since 2017 to October 2019
Have completed 111.06 miles of RTP resurfacing projects at a cost of $15,281,576
Repaired 4 slides at a cost of $969,024
Replaced 1 culvert at a cost of $540,113
From October to end of year, 2019
Will spend another $46,491,502 on 41.34 miles by end of 2019 on RTP resurfacing projects
Will repair 17 slides at a cost of $6,155,784
Secondary Roads Maintenance Initiative (as of October 17, 2019)
Paved 214.41 miles
Ditched 676.44 miles
Mowed 2,524.91 miles
Patched 844.59 miles
District Four
Roads to Prosperity (RTP) projects
Since 2017 to October 2019
Have completed 137.15 miles of RTP resurfacing projects at a cost of $12,560,669
Replaced 1 bridge at a cost of $199,473
Repaired 15 slides at a cost of $3,400,819
Replaced 2 culverts at a cost of $301,907
From October to end of year, 2019
Will spend another $5,233,851 on 32.81 miles by end of 2019 on RTP resurfacing projects
Will replace 4 bridges at a cost of $11,414,802
Will repair 11 slides at a cost of $4,833,975
Will replace 2 culverts at a cost of $657,181
Secondary Roads Maintenance Initiative (as of October 17, 2019)
Paved 145.31 miles
Ditched 881.60 miles
Mowed 2,126.65 miles
Patched 1,000.50 miles
District Five
Roads to Prosperity (RTP) projects
Since 2017 to October 2019
Have completed 80.54 miles of RTP resurfacing projects at a cost of $13,980,241
Repaired 1 slide at a cost of $500,000
Replaced 1 culvert at a cost of $112,690
From October to end of year, 2019
Will spend another $5,158,500 on 33.92 miles by end of 2019 on RTP resurfacing projects
Will replace 1 bridge at a cost of $400,000
Will repair 11 slides at a cost of $3,898,826
Secondary Roads Maintenance Initiative (as of October 17, 2019)
Paved 114.38 miles
Ditched 356.45 miles
Mowed 3,325.58 miles
Patched 813.20 miles
District Six
Roads to Prosperity (RTP) projects
Since 2017 to October 2019
Have completed 28.03 miles of RTP resurfacing projects at a cost of $9,039,264
Repaired 13 slides at a cost of $1,951,000
From October to end of year, 2019
Will spend another $1,388,200 on 11.59 miles by end of 2019 on RTP resurfacing projects
Will replace 3 bridges at a cost of $26,142,811
Will repair 19 slides at a cost of $2,758,800
Secondary Roads Maintenance Initiative (as of October 17, 2019)
Paved 82.77 miles
Ditched 112.39 miles
Mowed 243.81 miles
Patched 145.85 miles
District Seven
Roads to Prosperity (RTP) projects
Since 2017 to October 2019
Have completed 99.60 miles of RTP resurfacing projects at a cost of $75,453,576
Replaced 3 bridges at a cost of $4,267,463
Repaired 10 slides at a cost of $3,407,985
Replaced 2 culverts at a cost of $1,759,451
From October to end of year, 2019
Will spend another $3,478,000 on 29.58 miles by end of 2019 on RTP resurfacing projects
Will replace 1 bridge at a cost of $816,285
Will repair 8 slides at a cost of $2,127,915
Secondary Roads Maintenance Initiative (as of October 17, 2019)
Paved 69.05 miles
Ditched 820.53 miles
Mowed 3,461.18 miles
Patched 1,316.06 miles
District Eight
Roads to Prosperity (RTP) projects
Since 2017 to October 2019
Have completed 135.35 miles of RTP resurfacing projects at a cost of $9,546,458
Replaced 1 bridge at a cost of $234,484
Repaired 6 slides at a cost of $1,345,821
Replaced 1 culvert at a cost of $909,817
From October to end of year, 2019
Will spend another $2,091,000 on 36.35 miles by end of 2019 on RTP resurfacing projects
Will replace 1 bridge at a cost of $970,322
Will repair 10 slides at a cost of $1,283,000
Secondary Roads Maintenance Initiative (as of October 17, 2019)
Paved 60.17 miles
Ditched 1,180.89 miles
Mowed 2,904.86 miles
Patched 682.31 miles
District Nine
Roads to Prosperity (RTP) projects
Since 2017 to October 2019
Have completed 86.15 miles of RTP resurfacing projects at a cost of $15,944,810
Replaced 3 bridges at a cost of $3,647,690
Repaired 6 slides at a cost of $1,212,839
Replaced 2 culverts at a cost of $742,807
From October to end of year, 2019
Will spend another $11,466,517 on 11.96 miles by end of 2019 on RTP resurfacing projects
Will repair 6 slides at a cost of $2,054,929
Secondary Roads Maintenance Initiative (as of October 17, 2019)
Paved 95.90 miles
Ditched 704.28 miles
Mowed 3,736.39 miles
Patched 316.19 miles
District Ten
Roads to Prosperity (RTP) projects
Since 2017 to October 2019
Have completed 176.68 miles of RTP resurfacing projects at a cost of $41,011,160
Replaced 4 bridges at a cost of $3,367,627
Repaired 9 slides at a cost of $7,744,475
Replaced 1 culvert at a cost of $259,604
From October to end of year, 2019
Will spend another $1,883,448 on 19.76 miles by end of 2019 on RTP resurfacing projects
Will replace 1 bridge at a cost of $2,595,497
Will repair 13 slides at a cost of $1,888,448
Will replace 1 culvert at a cost of $713,710
Secondary Roads Maintenance Initiative (as of October 17, 2019)
Paved 60.09 miles
Ditched 968.99 miles
Mowed 3,444.32 miles
Patched 1,836.84 miles