I-70 Bridges Project Update Week of 3/30/2020

4/3/2020
​I-70 Bridges Project Update: Week of 3/30/2020

CHARLESTON, WV-

Continuing its commitment to transparency, the West Virginia Department of Transportation offers the following weekly update on the I-70 Bridges Projects in Ohio County for the week of March 30, 2020, following a two week pause by the contractor.

Below is a review of the work that has taken place on the project and work scheduled for the coming week:

Week of 3/30/2020

I-70
  • Sections A and C Westbound crossovers were in effect.
  • Westbound lanes were closed from Exit 2A through the span of Fulton Bridge.
    • As a part of this long-term closure, the Oglebay Park I-70 Westbound Entrance Ramp (Exit 2A) and the 16th Street Ramp (Exit 1B) to US 250/WV 2 were also closed.

Look Ahead to Week of 4/6/2020

I-70
  • Construction will continue in Sections A and C Westbound where crossovers are in effect.
  • Westbound lane closures from Exit 2A through the span of Fulton Bridge will continue
    • As a part of this long-term closure, the Oglebay Park I-70 Westbound Entrance Ramp (Exit 2A) and the 16th Street Ramp (Exit 1B) to US 250/WV 2 are also closed. 


Motorists are advised to be alert for changing traffic patterns and expect delays. Any questions or concerns regarding the I-70 Bridges Project can be directed to the hotline at (304)810-3214. Please note that inclement weather or other unforeseen circumstances could change the project schedule. For additional information regarding this project, please visit www.i70forward.com.


​​​