Proposed 4-lane partial access control highway from Man to Logan; approximate length of 12.5 miles
  
Purpose and Need Report completed May 1996
  
30-mile Corridor from Logan to Gilbert, following WV 73, WV 10 and WV 80, designated as part of National Highway System  by FHWA in 1998
  
Construction of 4-lane completed for WV 73 and segment of WV 10 between US 119 and Logan
  
FHWA approved reevaluation of Categorical Exclusion Evaluation March 2002
  
Estimated total cost of Logan to Man segment is $396.9 million (2002 estimate) including engineering, right-of-way and construction; estimated total construction cost is $349.5 million ($27.2 million per mile.)