Northbound and southbound lanes of US 52 will be closed between the hours of 8 p.m. Monday, October 7, 2025, and 6 a.m. Tuesday, October 8, 2025, to allow for a traffic switch of US 52 N onto the new James River Road Overpass Bridge.
During the closure, traffic will follow the posted temporary detour route signs, which utilize US 60 and Interstate 64 Exit 15 (29th Street). After completion of this work, James River Road Overpass Bridge will reopen with changes for northbound traffic. Phase 5 flow will be similar to the prior phase but alignment will be shifted for northbound traffic onto the outside lane of the newly constructed bridge. Median work will begin between northbound and southbound traffic.
Drivers are advised to use extreme caution when traveling, watch for slow or stopped traffic and follow all posted signs. Law enforcement will be on site to assist in keeping the work site safe.