A project to repave a nearly seven-mile stretch of four-lane Corridor G (US 119) in Mingo County is among 19 paving projects and several bridge projects awarded by the West Virginia Division of Highways (WVDOH) on Friday, December 1, 2023. The awards are from a bid letting conducted by the West Virginia Division of Highways (WVDOH) on Tuesday, November 14, 2023.
 
West Virginia Paving Inc. was low bidder on the project to repave all four lanes of Corridor G from Myrtle to the Logan County line, a distance of 6.85 miles. The bid amount was $13,882,788.35.
 
Other projects awarded on Friday, December 1, 2023, include:
 
  • Green Acres Contracting Company Inc. was the low bidder on a project to replace guardrails in District 3, with a bid of $695,260. (Calhoun, Jackson, Pleasants, Ritchie, Roane, Wirt, and Wood counties)
  • West Virginia Paving Inc. was the low bidder on a project to repave Corridor G from Myrtle to the Logan County line, with a bid of $13,882,788.35. (Mingo County)
  • BTI Contracting Inc. was the low bidder on a paving project on WV 80 from Gilbert to the Logan County line, with a bid of $3,144,189.95. (Mingo County)
  • Belt Paving Inc. was the low bidder on a paving project on WV 29 from Rio to Deep Run Hollow, with a bid of $925,163.69. (Hampshire County)
  • BTI Contracting Inc. was the low bidder on a paving project on Moses Fork Mountain on WV 152, with a bid of $891,305.15. (Wayne County)
  • West Virginia Paving Inc. was the low bidder on a paving project on WV 10 from Sarah to Melissa, with a bid of $2,065,858.88. (Cabell County)
  • West Virginia Paving Inc. was the low bidder on a paving project on WV 3 from Whitesville to the Raleigh County line, with a bid of $697,222.70. (Boone County)
  • SQP Construction Group Inc. was the low bidder on a project to install curb ramps on US 60 (Fifth Avenue) in Huntington, with a bid of $946,887. (Cabell County)
  • Kelly Paving Inc. was the low bidder on a paving project on WV 68 (Emerson Avenue) in Parkersburg, with a bid of $1,736,363. (Wood County)
  • Jim Construction Inc. was the low bidder on a project to install sidewalks and parking for the Hatfield McCoy Trail at the Hatfield Cemetery, with a bid of $986,901. (Logan County)
  • West Virginia Paving Inc. was the low bidder on a paving project on WV 62 from Longdale to the Jackson County line, with a bid of $1,234,387. (Mason County)
  • Triton Construction Inc. was the low bidder on a project for renovations to the ramps on US 250 at the intersection of US 250 and WV 2 in Wheeling, with a bid of $463,000. (Ohio County)
  • Charles J. Merlow Inc. was the low bidder on a deck replacement project on the Market Street Bridge in Wheeling, with a bid of $1,351,000. (Ohio County)
  • Mountaineer Contractors Inc. was the low bidder on a paving project on WV 18 from Greenwood Road to Sistersville, with a bid of $1,987,087.10. (Tyler County)
  • West Virginia Paving Inc. was the low bidder on a paving project on WV 19 from Canvas to Lost Road, with a bid of $1,357,299.12. (Nicholas County)
  • West Virginia Paving Inc. was the low bidder on a paving project on US 33 from Upper Isner to Kelly Mountain, with a bid of $5,482,518.63. (Randolph County)
  • Davis H. Elliot Construction Company Inc. was the low bidder on a project to install lighting fixtures along Corridor G from Jefferson Road to Oakhurst Drive, with a bid of $3,300,529.20. (Kanawha County)
  • Meadows Stone & Paving Inc. was the low bidder on a paving project on WV 16 from the Nicholas County line to Lizemores, with a bid of $966,143.45. (Clay County)
  • Kelly Paving Inc. was the low bidder on an intersection construction and paving project at the intersection of US 40 and Mt. DeChantal Road, with a bid of $959,934.06. (Ohio County)
  • J.F. Allen Company was the low bidder on a paving project on WV 74 from Cox’s Mill to Auburn Road, with a bid of $566,215.49. (Gilmer County)
  • BTI Contracting Inc. was the low bidder on a paving project on WV 75 from Sweet Run to Buffalo Creek, with a bid of $1,493,419.01. (Wayne County)
  • Meadows Stone & Paving Inc. was the low bidder on a paving project on WV 16 from Dundon to Clay Junction, with a bid of $389,905.07. (Clay County)
  • Catts Construction Inc. was low bidder on a renovation project on the Sheriff Fred Gaudet Bridge on US 33, with a bid of $407,117. (Upshur County)
  • Elite Contractors Inc. was the low bidder on a cleaning and painting project on the Glade Fork Bridge over Interstate 77, with a bid of $707,580.10. (Raleigh County)
  • J.F. Allen Company was the low bidder on a paving project on Old Weston Road, with a bid of $533,482.78. (Upshur County)
  • Mountaineer Contractors Inc. was the low bidder on a paving project on Burrough Street in Morgantown, with a bid of $650,570.35. (Monongalia County)
  • Mountaineer Contractors Inc. was the low bidder on a ramp paving project on Interstate 79, Exit 152, with a bid of $661,548.26. (Monongalia County)
  • J.F. Allen Company was the low bidder on a project to add turning lanes on Webster Road, with a bid of $11,760,146.66. (Nicholas County)
  • Doss Enterprises Inc. was the low bidder on a paving project on US 50 from Evansville to Fellowsville, with a bid of $988,488.75. (Preston County)
  • Elite Contractors Inc. was the low bidder on a cleaning and painting project on the Sullivan Road Bridge, with a bid of $1,250,806. (Raleigh County)
  • Tempo Construction LLC was the low bidder on a renovation project on the Big Buzzard Bridge, with a bid of $108,330. (Mason County)
 
Several factors are considered before awarding a bid, including whether a bid falls above or below the WVDOH Engineer’s Estimate and by what percentage. In cases where a bid is above the Engineer’s Estimate, WVDOH must consider the project need, repercussions of not awarding the project, additional funding sources, and whether sufficient reasons exist for the differences in estimates. Most projects are reviewed, analyzed, and awarded within a week of the bid letting, but the process can take longer.
 
When the Division of Highways has a project that is determined to be best constructed by a contractor, it is processed through the bid letting system. A letting is a scheduled opportunity for contractors to review and bid on several construction projects at one time. Lettings are held either once or twice per month and conducted through the Bid Express System online at www.bidx.com and handled through the Contract Administration Division. Contractors need to subscribe to Bid Express before bids can be accepted on any project.